摘要
为了防范投标人采取不平衡报价策略给业主的投资控制带来风险,在分析不平衡报价特征的基础上,针对投标人可能会采取的投标策略,给出了投标文件工程量清单中的主要单价合理性计算公式,并运用层次分析法基本原理,结合多目标决策理论中的逼近理想解排序法,建立了AHP-TOPSIS投标报价综合评判模型。通过工程实例验证,该方法对于投标人单价合理性的判断和识别具有可行性和有效性。
In order to prevent the risks of owner's investment control from unbalanced bidding strategies of the tenders,the rationality of the main price formulas in the bil l of quantities of the tender documents were given in this study based on analyzing the characteristics of unbal-anced bidding strategies and aiming at the bidding strategies adopted by the tenders. The synthetic estimation model of AHP-TOPSIS was also built through employing basic principles combining with TOPSIS of Multi-Objective Decision Theory. I t is feasible and effective for this meth-od to judge and identify the price rationality of tenders with the help of verification of the practical project application.
作者
聂相田
王帅
罗刚
NIE Xiangtian WANG Shuai LUO Gang(i.North China University of Water Resources and Electric Power,Zhengzhou 450011,China China Three Gorges Construction Management Co., Ltd,Chengdu 610041,China)
出处
《人民黄河》
CAS
北大核心
2017年第6期115-117,129,共4页
Yellow River
关键词
不平衡报价
合理性评判
AHP-TOPSIS模型
工程投标
unbalanced bidding
evaluation of reasonable price
evaluation model of AHP-TOPSIS
bidding for project construction