摘要
结合工程实例,根据在大截面异形钢骨混凝土梁施工中实际情况,运用CAD及BIM技术对现场钢筋绑扎、模板支设进行建模预排布模拟施工,合理安排施工工序,确保工程质量,加快施工进度,降低工程成本,取得了明显的经济效益。
In combination with the project, according to actual situation in the construction of large crosssection special-shaped steel reinforced concrete beam, the CAD and BIM technology are used on the steel binding, formwork for modeling configuration simulation construction, reasonable arrangement of construction process to ensure the engineering quality, speed up the construction progress and reduce the engineering cost, it achieves obvious economic benefits.
出处
《施工技术》
CAS
北大核心
2017年第11期141-143,共3页
Construction Technology
关键词
钢骨梁
异形截面
模板
钢筋绑扎
施工技术
steel frame beams
special section
formwork
reinforcement banding
construction