在设备安装前准备,设备装车运输,安装硐室位置选择,支架组装、卸车、调向以及组装程序优化等方面加强管理,81209综采工作面设备安装时间由原来1.5个月缩短为20天。
The paper introduces the fast installation methods of mechanical equipment at 81209 fully-mechanized working face from aspects of preparation before installation, equipment loading, position selection of installation chamber, support assembling, unloading and steering, and assembling procedure optimization, which have shortened the equipment installation period from 1.5 months to 20 days.