泰州二期1000 MW超超临界二次再热机组建设与运行 被引量:12

Construction and Operation of the 1 000-MW Ultra-Supercritical Double Reheat Unit in Taizhou Ⅱ
下载PDF
导出
摘要 阐述了1 000 MW二次再热燃煤发电机组的选型和参数确定原则,通过产学研用、严谨论证,推动重大技术创新方案和示范工程落地,探索了机组建设中的技术风险管控和工程管理要点,介绍了精细化管理、洁净化安装、全过程质量管理、精细化调试的关键要点。工程投产后,持续做好运行优化和运行管理,实现了示范工程全面达到各项性能指标,项目的建设和运行对促进中国高效清洁火力发电装备技术水平的提升,促进燃煤的清洁利用,都将具有良好的示范作用。 This paper describes the type seleqtion and parameter determination principles of the 1 O00-MW double reheat coal-fired power generation units. Through studies and rigorous demonstration, as well as the promotion of major technological innovation programs and the implementation of the demonstration project, the paper explores the technical risk control and project management points in the construction of the units. It also introduces the key points in the micromanagement, the clean installation, the process quality management, and the precise debugging. Since the operation, the operation optimization and management of the project have been sustained to satisfy all performance index requirements. The construction and operation of the project are demonstratively helpful for improving the technical levels of China' s efficient clean coal power generation equipments and the clean coal utilization.
出处 《中国电力》 CSCD 北大核心 2017年第6期38-42,48,共6页 Electric Power
基金 国家科技支撑计划项目(2012BAA12B00)~~
关键词 燃煤发电 1000MW 超超临界机组 二次再热循环 工程建设 运行 示范工程 coal-fired power generation 1000 MW uhra-supercritical unit double reheat cycle construction operation demenstrationpower plant
  • 相关文献

同被引文献112

引证文献12

二级引证文献64

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部