污水厂作为城市污水处理的基础设施,是我国城市建设发展中关键的一环。而污水厂管道安装直接关系着污水厂后期污水处理工作的顺利运行,这就对污水厂管道安装施工技术提出了更高水平的要求。本文首先概述了污水处理流程,然后分别从施工准备阶段、施工阶段以及施工过程中的技术要点等内容来对污水厂管道安装施工技术进行分析与研究,从而提高其施工技术水平,提升工程质量。
As the infrastructure of urban sewage treatment, sewage treatment plant is a key link in the development of urban construction in china. The installation of the sewage treatment plant is directly related to the smooth operation of the sewage treatment in the sewage treatment plant. This paper first outlines the process of sewage treatment, and then from the construction preparation stage, construction stage and construction process of the technical points to analysis and Research on the sewage pipe installation and construction technology, so as to improve the level of construction technology, enhance the quality of the project.
出处
《中国资源综合利用》
2017年第5期15-17,共3页
China Resources Comprehensive Utilization
关键词
污水厂
管道安装
施工技术
sewage plant
pipeline installation
construction technology