摘要
众所周知,BIM技术的应用推广已成为必然发展趋势。传统的二维设计已无法满足直观与精细化设计的需求。本文以横沙岛集约化供水工程为例,将Geostation地质软件及Power Geopak设计软件应用到横沙岛集约化供水工程过江段的三维设计中,并对相关问题进行讨论,为以后非开挖定向钻进技术的三维设计提供实践基础。
As we all known, the application and development of BIM technology has become an inevitable trend. The traditional two-dimensional design was unable to meet the needs of intuitive and refined design. This paper takes Hengsha Island Water Supply Project as an example, Geostation software and Power Geopak design software were applied to the three-dimensional design of Hengsha Island Intensive Water Supply Project.The ideal modeling effect was displayed and issues were discussed. It provides foundation for 3D design of non-excavation directional drilling technology.
出处
《上海水务》
2017年第2期69-70,62,共3页
Shanghai Water