摘要
水电站的截流及围堰施工是水利水电工程施工的一个重要阶段,截流成功与否直接关系到工程建设的成败。文章以老挝南涧水电站南坝截流及围堰施工为例,阐述了施工期截流和围堰施工过程,为类似水电站工程施工提供参考依据。
The dam closure and cofferdam construction of hydropower station is an important stage in the construction of water conservancy and hydropower projects, which will directly influence the result of the project construction. Taking the dam closure and cofferdam construction of Nanjian hydropower station in Laos as an example, this paper expounds the construction process of closure and cofferdam during construction period, and provides reference for the similar hydropower station construction.
作者
严俊
Yan Jun(China Gezhouba Group International Engineering Co., Ltd., Beijing 100025, China)
出处
《江苏科技信息》
2017年第17期42-43,共2页
Jiangsu Science and Technology Information
关键词
南坝
截流
围堰
施工
south dam
closure
cofferdam
construction