摘要
化学和容积控制系统(CVS)是AP1 000核电站核岛重要辅助系统,根据CVS工作特点对补水管路容积的影响进行了计算分析,从安全性、经济性等方面对调硼后管路冲洗方法进行了探讨,指出了冲洗过程存在的问题,并提出了冲洗方法改进建议。
The Chemical and Volume Control System(CVS)is an important auxiliary system of AP1000 nuclear power plant.This paper calculates and analyzes the impact of the makeup pipeline volume according to the CVS operating characteristics,discusses the pipeline flushing methods after boron concentration adjustment from the perspective of security and economy,points out the problems existing in the flushing process,and finally puts forward the improvement suggestions about the flushing method.
出处
《电力与能源》
2017年第3期323-326,共4页
Power & Energy
关键词
CVS
调硼
冲洗
CVS
boron concentration adjustment
flushing