摘要
以上海市奉贤区S4南桥立交改造工程为背景,对现状立交拥堵原因进行分析,结合周边地块规划及现状控制因素,通过交通分析得出节点拥堵的原因,并提出需对现状节点进行改造,通过多方案对比分析,解决S4南桥立交节点方案问题。
Taking Shanghai Fengxian District S4 Nanqiao Interchange Reconstruction Project as the background,the article analyzes the present congestion cause of interchange.According to the planning and present control factor of the surrounding land,the article shows the cause of node congestion after the traffic analysis,points out it is necessary to reconstruct the present nodes.After the comparison and analysis of many schemes,the problems existing in the node scheme of S4 Nanqiao Interchange are solved.
出处
《城市道桥与防洪》
2017年第7期17-19,共3页
Urban Roads Bridges & Flood Control
关键词
立交改造
交通节点
方案比选
交通分析
S4高速公路
南桥立交
reconstruction of interchange
traffic node
scheme comparison
traffic analysis
S4 expressway
Nanqiao Interchange