摘要
文中针对尾矿库复杂场地平整问题提出一种基于Civil 3D的方法,并以某尾矿库实际工程为例,着重研究了应用该方法进行场地平整设计的全过程,计算成果直观、准确。通过对比工程竣工结算资料,表明该方法具备一定的实用价值。
A design method based on Civil 3D about the leveling problem for complicated ground of tailings pond was proposed. Combining with a project example of tailings pond, the whole process of designing ground leveling by the method were emphatically researched, and the calculation results were intuitive and accurate. Comparing to the pro- ject completion and settlement information, the leveling method had certain practical value.
作者
傅灿
文枚
李洪昌
Fu Can Wen Mei Li Hongchang(Kunming Prospecting Design Institute of China Nonferrous Metals Industry, Kunming 650051, China)
出处
《矿山测量》
2017年第3期125-128,共4页
Mine Surveying