成都绿地8号地块超高层项目采用全新的整体自顶升廻转式多吊机集成运行平台(廻转平台)进行塔楼施工,阐述了廻转平台吊机选择、支承顶升系统布置等要点,并阐述了廻转平台的施工及顶升过程中的关键技术。
A new technology of the auto-lifting & rotating platform with cranes group (ALRMCP) for the construction of tower structure is applied in Chengdu Greenland Tower. This paper describes the key point of crane selection and the arrangement of supporting lifting system. The key technology during the construction and lifting of rotating platform is also introduced in detail.