包钢大型高炉喷煤系统设计缺陷与改进措施 被引量:1

Design Defects and Improvement Measures of Pulverized Coal Injection System for Large Blast Furnace in Baotou Steel
下载PDF
导出
摘要 文章针对包钢两座大型高炉喷煤系统投产后遇到仓顶除尘器箱体严重变形、喷吹氮气消耗量大、喷吹支管、喷枪软连接频繁磨漏等问题,通过逐步完善生产工艺,改进设备缺陷,加固仓体,改善排风不畅,调整管路风喷嘴,降低喷吹用风量等方法,降低了能耗,解决了生产中的问题。 In this paper, it aims at the problems encountered after the commissioning of pulverized coal injection sys-tem for two large blast furnaces in Baotou Steel, such as serious silo deformation of roof scrubber, large consumption of ni-trogen injection, frequently worn - out of branch injection pipe and spray gun soft connection. By means of gradually impro-ving the production process, equipment defects and poor ventilation, strengthening the silo, adjusting the pipeline air noz-zle ,increasing operation methods, improving operation technique and reducing injection air volume to reduce the energy consumption and to solve the problems in production.
出处 《包钢科技》 2017年第3期17-19,共3页 Science & Technology of Baotou Steel
关键词 高炉喷煤 仓体变形、罐压操作、加压组件、支管磨损 blast furnace pulverized coal injection silo deformation tank pressure operation pressurizing assembly branch pipe wearing
  • 相关文献

同被引文献4

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部