某单线铁路桥 ,经检测发现明显质量缺陷 ,分析质量缺陷产生的原因 ,介绍桥墩加固施工方法 ,即原承台外侧增设钻孔桩 ,桩顶新建承台与原墩身固结 ,施工采用单壁钢围堰稳固墩位处河床 ,兼作钻孔桩平台支撑结构。
A single-track railway bridge had obvious quality disfigurements through inspection. The causes that lead to it were analyzed. The method of rehabilitation and strengthening of the pier was stated. The bored piles were constructed around original base slab, new base slab set up at the piles' top was firmly connected to original pier shaft. During construction the single wall steel cofferdam was not only adopted to stabilize the riverbed at that pier, but also used as a support structure of bored operation platform.