摘要
文章对克老双线隧道快速施工进行了探讨,通过三种开挖方案对比,最后提出了适合于中国特点的施工方法,并配合严格的施工组织和施工管理,创造了铁路双线隧道单口独头月成洞282.67 m的最高纪录,并连续八个月保持高进度,平均月成洞234.64 m。
By comparison of three excavation programs, the rapid excavation technology used in Kelao double -track tunnel is discussed. Finally the proper construction method is suggested. With this method, monthly advance rate of 282.67 m from one opening of double - track tunnel, which lasts 8 months, is created. The average monthly advance rate is 234.64 m.
出处
《现代隧道技术》
EI
2002年第4期57-61,共5页
Modern Tunnelling Technology
关键词
双线隧道
快速施工
施工技术
施工管理
Double - track tunnel
Rapid excavation
Construction technique
Construction management