TBM导轨吊点拆卸技术研究 被引量:2

Research of TBM Rail Lifting Point Disassembly Technology
下载PDF
导出
摘要 吐库二线中天山隧道左线TBM设备整体老化严重,已超过使用年限,再利用价值很低,采取破坏性拆卸。通过工序优化、受力可行性研究,改变原TBM大断面、桥式起重拆卸方式,缩小原拆卸洞断面,采用纵向导轨吊点结合电动葫芦进行吊装,成功用于工程实践,获得较好了的应用效果。 TBM equipment for left line of Tianshan Tunnel was aging seriously in the second line of Turpan to Korla, it was already over service life and reuse value was very low, so the measures of destructive disassemble were taken. Through process optimization and feasibility study of force, changing the original TBM large section and bridge lifting method, reducing the original demolition section, and lifting with vertical guide rail and electric hoist, it had been proved successfully in engineering practice, and good application effect was achieved.
作者 王慧英
出处 《铁道建筑技术》 2017年第6期124-128,共5页 Railway Construction Technology
基金 新疆自治区科技支疆项目计划(200991214)
关键词 TBM 报废 破坏性拆卸 导轨吊点 电动葫芦 TBM scrapping destructive disassembly lifting point of guiding rail electric hoist
  • 相关文献

参考文献11

二级参考文献39

共引文献47

同被引文献24

引证文献2

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部