摘要 近年来,随着我国轨道交通的快速发展,预制节段箱梁拼装工艺也因其施工质量高、施工周期短以及对交通影响小等优势,被广泛运用于城际轨道和公路桥梁建设中,并取得了很好的成就。然而在预制节段箱梁拼装过程中,总会由于各种原因而影响到施工质量,严重时还可能引发重大质量安全生产事故,给社会造成巨大损失。因此,在预制节段箱梁拼装过程中,一定要对可能影响施工质量的各种因素加以重视,从而推动我国交通运输的可持续发展。 In recent years, with the rapid development of transportation industry in China, precast segmental box girder assembly process also due to the high quality o fits construction, short construction period and traffic impact small advantages, widely using in our country the construction of highways and bridges, and made good achievements. However, in the assembly process of precast segmental box girder, there will always be a varietyofreasons to affect the construction quality, serious when it may cause a major safety accident, causing huge losses to the country. Therefore, the tel event construction enterprises must be in the precast segmental box girder assembly process, the construction quality of the various elements that may affect the quality of the construction, thus promoting the sustainable development o fChina's transportation industry.
作者 徐超湘
出处 《工程建设与设计》 2017年第15期175-176,179,共3页 Construction & Design for Engineering
关键词 预制 节段箱梁拼装 施工质量管理 控制措施 precast segmental box girder assembly construction quality management control measures
  • 相关文献

参考文献3

二级参考文献15

  • 1铁建设[2005]160号,铁路混凝土工程施工质量验收补充标准[s].
  • 2AASHTO. Guide Specifications for Design and Construction of Segmental Concrete Bridges[S]. Washington D. CUSA. Second Edition, 1999.
  • 3Takebayashi T, Deeprasertwong K, Leung Y W. A Full-Scale Destructive Test of a Precast Segmental Box Girder Bridge with Dry Joints and External Tendons[J].Structures and Buildings, Proceedings of Institution of Civil Engineers, 1994, 104(3) : 297-315.
  • 4Angel C Aparicio, Gonzalo Ramos, Juan R Casas. Testing of Externally Prestressed Conerete Beams[J]. Engineering Strue tures, 2002, 24(1): 73-84.
  • 5Rabbat B G, Sowlat K. Behavior of 1/5 Scale Segmental Con crete Girders with External and Internal Tendons[C]// External Prestressing in Bridges, ACI: SP-120, 1990. 305-314.
  • 6MacGregor R, Kreger M, Breen J E. Strength and Ductility of a Three-Span Externally Post Tensioned Segmental Box Girder Bridge Model[C]// External Prestressing in Bridges, ACI: SP-120, 1990: 315-338.
  • 7J Turmo, G Ramos, A C Aparicio. FEM Study on the Structural Behavior of Segmental Concrete Bridges with Unbonded Prestressing and Dry Joints: Simply Supported Bridges[J].En gineering Structures, 2005, 27(11): 1 652-1 661.
  • 8南京长江第四大桥建设协调指挥部,东南大学,中交公路规划设计院有限公司,等.南京长江第四大桥48m跨体内一体外混合配束节段预制拼装箱梁足尺模型试验研究报告[R].南京:2010.
  • 9TBl0002.1-2005,铁路桥涵设计基本规范[S].
  • 10铁建设[2005]160号,铁路客运专线桥涵工程质量验收标准[S].

共引文献30

同被引文献4

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部