某高层建筑物综合纠偏加固方法的应用 被引量:11

Application of a comprehensive method to rectify and reinforce a high-rise building
下载PDF
导出
摘要 本文对湿陷性黄土地区某高层建筑住宅楼的纠倾原因进行分析,提出了多竖井开挖分批水平掏土迫降+锚索加压调控+钢管桩与石灰桩加固的综合纠倾加固措施。通过科学合理的施工次序及现场监测,实践证明,该方法在湿陷性黄土地区治理建筑物不均匀沉降病害效果显著,保证了建筑物的长期稳定要求。对其他类似建筑物不均匀沉降的设计和施工具有指导性意义。 Based on the analysis of the causes of the dumping of a high-rise building in the collapsible loess area,a comprehensive reinforcement measures involving of multi-shaft excavation,soil digging horizontally,compression with pre-stressed anchor,column pile and ash column etc is proposed. Through scientific construction sequence and on-site monitoring,it has been proved that this method has a great effect on the uneven settlement of the building in the collapsible loess area,which ensures the long-term stability requirement of the building. It could be referred by the similar design and construction of uneven settlement of other similar projects.
出处 《工程勘察》 2017年第8期12-16,共5页 Geotechnical Investigation & Surveying
基金 中国中铁股份公司资助项目(2016KJ005-Z005-03) 甘肃省科技厅资助项目(144JTGA233)
关键词 建筑倾斜 纠偏加固 湿陷性黄土 building tilt rectification and reinforcement collapsible loess
  • 相关文献

参考文献8

二级参考文献48

共引文献71

同被引文献55

引证文献11

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部