摘要
结合海外某选矿厂项目实例,根据国际通用的项目进度管理程序,通过进度计划软件编制项目计划,使用S曲线直观的表述计划进度与实际进度。
Combining apractical case of a certain overseas beneficiation plant,and based on the internationally common project schedule management program,the paper shows the way of using S-curve to express the scheduled plan and real schedule straightly through the compilation of project schedule by program.
作者
于天亮
YU Tianliang(Northern Engineering & Technology Corporation, MCC, Dalian 116600, China)
出处
《矿业工程》
CAS
2017年第3期1-2,共2页
Mining Engineering
关键词
海外项目
WBS
进度计划
S曲线
进度管理
overseas project
WBS
scheduled plan
S-curve
schedule management