摘要
新建地铁工程信号系统的调试工作是直接关系到能否按期实现运营的重要环节。由于合肥轨道交通1号线前期工程的影响,信号系统的作业面不能按原定计划交付,故需根据工程实际进展情况进行调试进度计划策划。以该线地铁前期工程交付的作业面来制定信号系统调试进度计划,并根据实际进程进行控制,以保证信号系统调试能按计划在规定的时间节点实现。
The signaling system commissioningof a newly built metro line is a key to the operation on schedule. Due to the delay in the first phase construction of Hefei rail transit Line 1, the signaling system cannot be delivered as scheduled and thus needs a new commissioning plan accord- ing to the practical construction process. The new schedule should be made according to the actual process control to make sure that the project could be delivered on the decided time node.
作者
谢树庆
XIE Shuqing(Hefei Urban Rail Transit Co., Ltd., 230001, Hefei, China)
出处
《城市轨道交通研究》
北大核心
2016年第B07期71-74,共4页
Urban Mass Transit
关键词
地铁
信号系统
调试
进度计划
策划
metro
signaling system
commissioning
schedule plan
planning