摘要
对云南水富30×10~4m^3/d液化天然气装置在建成调试及试生产过程中出现的主要问题进行分析,如何采取的解决措施,以及为满足装置安全生产运行所作的技术改造进行总结。
The main problem of this Yunnan Shuifia 30 * 104m3/d liquefied natural gas plant in the completion of commissioning and trial production process in the analysis of how to take measures to meet the technology and device for safety operation summary.
出处
《云南化工》
CAS
2017年第7期70-72,共3页
Yunnan Chemical Technology