考虑灌溉用水集中度下田间水池调节容积分析 被引量:1

Calculating the Volume of Regulating Field Water Pool under Intensive Irrigation at Specific Time Periods
下载PDF
导出
摘要 目前灌溉田间水池的设计按照轮灌制度进行,但实际灌溉中普遍存在农户集中用水现象。针对该矛盾,通过理论推求,给出了上午和下午2个梯形高峰集中用水过程下调节容积的计算方法,对比分析了完全轮灌和考虑集中用水情况下的田间水池调节容积大小。结果表明,考虑集中用水情况下所需的田间水池调节容积大于完全轮灌情况,应用示例中,和完全轮灌相比,典型梯形用水过程下水池调节容积增加了14.82%。在灌溉系统水池调节容量设计时应充分考虑随机用水情况,以保障正常灌溉作业。 Current design of regulating-water pool in the field assumed the irrigation is rotational, while m reality- farmers often use the water during some specific time periods. In order to resolve this dilemma between design and use, this paper presented a new method to calculate how to adjust the pool volume assuming the daily change of intensive water use with time was two trapezoidal shapes, one in the morning and one in the aftemoon. We compared the pool sizes calculated considering both normal rotational irrigation and intensive irrigations at specif- ic times. The results showed that the pool volume for intensive irrigation was larger than that for rotational irriga- tion, and for a typical trapezoidal shape of water-use process, the pool volume needed to be enlarged by 14.82%. Hence, in designing the water pool, its volume should be calculated based on the real demand for irrigation to ensure safe and reliable operation of the irrigation system.
出处 《灌溉排水学报》 CSCD 北大核心 2017年第8期59-64,共6页 Journal of Irrigation and Drainage
基金 国家“十二五”科技支撑计划课题(2014BAD12B06,2014BAD12B05) 中国水科院团队建设类项目(节基本科研KY1788)
关键词 灌溉设计 田间水池 轮灌 集中用水 irrigation design field water pool rotational irrigation peak water consumption
  • 相关文献

参考文献2

二级参考文献18

  • 1尹正杰,王小林,胡铁松,陈鲁莉,武夏宁.灌区田间灌溉蓄水工程的规模优选[J].农业工程学报,2006,22(1):53-57. 被引量:2
  • 2王平.灌溉水库兴利调度图长系列计算方法的改进[J].中国农村水利水电,1997(7):24-27. 被引量:20
  • 3Potter K W. Sequence peak procedure: minimum reservoir capacity subject to constraint on final storage [J].Water Resour Bull, 1977,13(3):521-528.
  • 4Loucks D P, Stedinger J R, Haith D A. Water resources systems planning and analysis[M]. New York t McGraw-Hill, 1981.
  • 5马文正.灌溉水库最优规划研究[J].武汉水利电力学院学报,1984,17(3):97-105.
  • 6Schwartz S S. Multiobjective management of Potomac River consumptive use[J]. J of Water Resour, Plng and Mgmt, 2000,126(5):277-287.
  • 7Houck M H. A chance-constrained optimization model for reservoir design and operation [J]. Water Resour Res,1979,15(5):1011-1016.
  • 8Afshar A, Marino M A, Abrishamchi A. Reservoir planning for irrigation district [J]. J of Water Resour,Plng and Mgmt, 1991,117(1):74-85.
  • 9Colorni A, Fronza G. Reservoir management via reliability programming[J]. Water Resour Res, 1976, 12(1):85-88.
  • 10Revelle C S. Optimizing reservoir resources: including a new model for reservoir reliability [M]. New York:Wiley, 1999.