地下洞室采空区涌水段开挖施工方法

Excavation construction methods for water gushing section of underground caverns goaf
下载PDF
导出
摘要 采空区涌水段开挖施工前先进行深孔超前探排水孔钻探,探明掌子面前方及洞顶的水量大小,排水后再进行掘进施工。以"先探后掘"、"管超前、短进尺、弱爆破、少扰动、强支护"为原则,进行隧洞的开挖支护施工。 Before the excavation construction for water gushing section of underground caverns goaf,deep holes should be drilled first to make preparations for drainage in advance,ascertaining water quantity in front of tunnel face and on the top of caverns,draining water and then conducting driving construction. The principle of " prospecting first,then driving construction,casing ahead of time,short drilling footage,weak blasting,less disturbing,strong supporting" should be followed,proceeding the excavation construction of the tunnel.
作者 张伟
出处 《黑龙江水利科技》 2017年第6期117-119,共3页 Heilongjiang Hydraulic Science and Technology
关键词 隧洞 采空区 处理措施 开挖支护 短进尺若爆破 tunnel goaf treatment measure short drilling footage weak blasting
  • 相关文献

参考文献1

二级参考文献8

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部