期刊文献+

陆上风电场工程EPC总承包特点分析 被引量:3

Characteristics of the EPC Contracting Land Wind Farm Projects
下载PDF
导出
摘要 陆上风电场工程采用EPC总承包施工的难点是,设计、采购、施工三个方面交叉影响大,对各分包队伍及设备厂家的多重管理,进度与质量控制的难度较大。根据实践经验,建议采取以下主要措施,制定详细的项目策划书和详细的EPC项目总体与分步进度计划书,建立项目质量保证体系,编制应急救援预案,项目部统筹领导与后方资源及技术支持进行全面协调等。 For land wind farm projects, difficulties are frequently encountered to adopt the engineering-procurement-con-struction (EPC) contracting mode, including the influence of the interactions among the engineering, procurement and construction processes, the muhiple management of subcontractors and equipment manufacturers, and the difficulties in the schedule and quality control. According to the practical experience, countermeasures are proposed, such as the de-velopment of the detailed project plan, the development of detailed overall and step-by-step EPC schedules, constructionof the quality control system, preparation of the emergency response plan, the overall management of the project depart- ment, and the comprehensive coordination of the resources and technical support departments.
作者 张坤
出处 《水电与新能源》 2017年第8期72-74,共3页 Hydropower and New Energy
关键词 EPC总承包 施工重点难点 应对措施 EPC contracting key and difficult points of construction countermeasures
  • 相关文献

参考文献1

共引文献13

同被引文献10

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部