摘要
根据生产现状,进行移设规划研究。提出了横向和纵向上技术可行的多个布置方案,建立数学模型,并对各方案的技术可行性、经济合理性和对远期的影响进行了研究论证,最终确定了破碎站下一个合理布置位置为地表境界南部+1 075 m水平南坪沟附近,最优移设步距为2.05km,移设周期为5 a左右。
According to the production status, the article carries out transfer planning research, proposes a number of layout schemes which are feasible in the horizontal and vertical directions, and establishes mathematical model, studies and demonstrates the technical feasibility, economic rationality and long-term impact of the various programs. The final reasonable location of the crushing station is for the surface of the south +1 075 m level near Nanpinggou. The optimal shift step distance is 2.05 km, and the shift period is about 5 years.
出处
《露天采矿技术》
CAS
2017年第8期5-9,共5页
Opencast Mining Technology
基金
中国煤炭科工集团科技创新基金面上项目资助(2016ZYMS019)
关键词
破碎站
移设规划
移设步距
crushing station
transfer planning
shift step distance