某金矿矿仓治理研究 被引量:3

Research on the Ore Bunker Treatment of a Gold Mine
下载PDF
导出
摘要 矿仓是地下金属矿山的咽喉工程。矿石在转运过程中相互冲击、磨损,易造成矿仓塌方事故。矿仓运行状态良好对矿山企业的持续稳定发展具有重要影响。以某金矿仓的修复治理工程为例,详细介绍了矿仓的破坏机理以及治理方案的选择。通过比较跟管注浆法、分层浇筑法和新建矿仓3种治理方案的优缺点,指出跟管注浆法治理效果最优且工期最短,因此选择跟管注浆法对原矿仓进行治理,对类似矿山工程的治理具有一定的借鉴意义。 Ore bunker is the throat project of underground metal mine.During the process of transportation,the ore is lashing and abrasion each other,which is easy to cause collapse accident of ore bunker.The good running state of ore bunker has an important influence on sustained and stable development of mine enterprise.Taking the repair of ore bunker of a gold mine as an example,the failure mechanism of ore bunker and selection of treatment scheme are introduced in detail.By comparing the advantages and disadvantages of three treatment schemes,including pipe grouting method,layered casting method and newly-built ore bunker,the results show that pipe grouting method has the best treatment effect and shortest duration,finally pipe grouting method is adoped to treatment ore bunker,it has a certain reference for engineering treatment of similar mines.
作者 丁剑锋 DING Jianfeng(Qilu Mining Department of Shandong Gold Mining Co., Ltd., Laizhou 261400, Shandong, China)
出处 《黄金科学技术》 CSCD 2017年第4期52-57,共6页 Gold Science and Technology
关键词 矿仓治理 跟管注浆法 修复工程 矿仓塌方 金属矿山 山东省 ore bunker treatment pipe grouting method repair project collapse of ore bunker metal mine Shandong Province
  • 相关文献

参考文献5

二级参考文献30

  • 1葛宝臻,卢波,田庆国,杜朴,吕且妮.激光三维扫描数据的表面重建[J].计算机测量与控制,2006,14(10):1366-1367. 被引量:12
  • 2季翱,宋卫东,杜翠凤,王永清,兰建强.采区溜井严重垮冒原因分析及加固方案研究[J].金属矿山,2007,36(2):26-28. 被引量:21
  • 3设计手册编写组.钢筋混凝土结构设计手册[M].北京:建筑工业出版社,1993..
  • 4北京科技大学.程潮铁矿2^#主溜井特大塌方治理综合技术研究报告[M].北京:北京科技大学,1998..
  • 5罗周全,张保,刘晓明,杨承祥.基于CMS精密探测的采场贫化损失计算方法[J].金属矿山,2007,36(10):84-88. 被引量:26
  • 6Gong J Y,Cheng p g,Wang D Y. Three dimensional modeling and application in geological exploration engineering [J]. Computers & geosciences, 2004,30 (4) : 391-404.
  • 7Esmaieli K, Hadjigeorgiou .J ,(h'enon M.Stabilily analysis of the 19A ore pass at Brunswick Mine using a two-stage numerical modeling approach [J ].Rock Mechanics and Rock Eengineering, 2013,46( 6 ) : 1323-1338.
  • 8Remennikov A M, Mutton V, Nimbalkar S,el aI.Experinlental and numerical invesligation of high-yield groul ore pass plugs to resist impact Ioads[J ].lnternal ional Join'hal ,f Rock Mecha- nics and Mining Sciences, 2014,70 : 1 - 15.
  • 9Silva Filho A B,Silva J M, Curi A.Efeil++ da ,'t,gosidade reco- rtada polida no eseoamento em modet de passagem detain- 6 rin [ J].Minas, Ouro Preto, 201 0, 63 ( 4 ) : 633-638.
  • 10Larson M K,lverson S H,SlewarI B M,el al.Preliminm), asse- ssment of pariiele flow code as a tool fo assess ore pass saly [J].lnternational Jom'nal of Rock Mechanics and Mining Sclence,s, 1998,35 ( 4 ) : 533.

共引文献36

同被引文献8

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部