摘要
本文主要依托新建福州至平潭铁路平潭海峡公铁两用大桥基础施工,详细地介绍了台风区跨海桥梁基础施工难点,针对施工难点进行技术研究,并形成一系列的成果,为以后类似条件下跨海桥梁基础施工提供了良好的借鉴。
Based on the foundation construction of newly-built Pingtan Strait Road-rail Bridge from Fuzhou to Pingtan Railway,this paper introduced in detail of the difficulty for foundation construction of sea-crossing bridge in typhoon area.Then,it made a technical research against the construction difficulties,and formed a series of achievements,which could offer good reference for foundation construction of sea-crossing bridge in future similar conditions.
出处
《铁道建筑技术》
2017年第8期1-4,36,共5页
Railway Construction Technology
基金
中国铁建股份有限公司科技研究开发计划项目(14-A01)
关键词
平潭海峡公铁两用大桥
台风区
跨海桥梁基础
埋置式平台
两快一抗
钢吊箱
桩周土体
Pingtan Strait Road-rail Bridge
typhoon area
sea-crossing bridge foundation
embedded platform
two-quick one-resistant
steel hoisting box
soil around pile