摘要
针对观音岩水电站下闸蓄水难点,通过科学制定下闸程序、优化下闸时机、细化方案、协调上游电站控泄、构建组织保障、做好供水沟通等关键措施,确保了电站顺利下闸蓄水,圆满完成2014年12月首台机组发电目标。
Smooth tail lock impoundment is ensured aiming at difficulties of tail lock water impoundment in Guanyinyan Hydropower Station through scientifically formulating tail lock procedures,opportunity,refining plan,coordinating flow discharge control of upstream power station,constructing organization guarantee,doing well in water supply communication and other key measures. The first unit power generation objective was smoothly completely in December 2014.