从道路快速化改造工程实施需求和综合管廊本身功能定位出发,详细阐述了长沙市湘府西路综合管廊工程的设计内容,主要包括综合管廊横断面设计、平面布置、竖向设计、结构设计、附属设施设计及施工方法,该工程将道路两侧高压架空线纳入综合管廊,为长沙重要主干路湘府路的快速化改造提供了重要施工建设条件。
Based on the requirement of road rapid development and the function of utility tunnel, taking the design of Xiangfuxi Road utility tunnel project in Changsha City as an example, the design process was described in detail. The design contents of the project included the cross section design, plane layout, vertical design, structure design, subsidiary facilities design and construction methods. In the process of project implementation, the high voltage overhead lines on both sides of the road were taken into the utility tunnel, which provided important construction conditions for the rapid transformation of Xiangfu Road, an important main road in Changsha City.
出处
《中国给水排水》
CAS
CSCD
北大核心
2017年第18期73-77,共5页
China Water & Wastewater
关键词
综合管廊
高压架空线缆化
防火分区
附属设施
utility tunnel
high vohage overhead cable
fire compartment
subsidiary facilities