我国承建俄罗斯莫斯科至喀山高速铁路工程,按合同约定,需采用俄罗斯铁路工程概预算编制办法及配套定额编制初步设计概算。但俄罗斯铁路工程定额没有与高铁工程配套的有关施工机械台班定额。此文以900 t架桥机为例,详细阐述进口施工机械其台班费的计算方法。
The Moscow to Kazan high-speed railway project is built by our country. And according to the contract,the preliminary design estimates should be prepared based on the railway engineering budget preparation method and matching quota of Russia. But there is not the machine-team quota of construction machinery matching with high-speed railway project in railway engineering quota of Russia. Taking the 900 t imported bridge erecting machine as an example,the computing method of machine-team expense of imported machine are elaborated.