期刊文献+

挑水河磷矿条带充填开采胶结充填体强度设计研究 被引量:2

Design of strength of cemented fill in strip-filling mining in Tiaoshuihe Phosphate Mine
下载PDF
导出
摘要 针对挑水河磷矿的实际情况,采用条带充填开采方法。运用两区约束理论及有效区域理论,推导了条带充填开采胶结充填体强度的计算公式。通过工程类比法及理论分析计算,确定了采空区胶结充填体的强度。 The strip-filling mining method is introduced in the light of the actual conditions of Tiaoshuihe Phosphate Mine. The formula for calculating the strength of cemented fill in strip-filling mining is derived based on the theory of two-zone constraints and the effective region theory and the strength of cemented fill in mined-out area is determined by the engineering analogy method and the theoretical analysis method.
作者 梅志恒 李延杰 孟恒 王学梁 郑桂春 MEI Zhi-heng LI Yan-jie MENG Heng WANG Xue-liang ZHENG Gui-chun(Hubei Provincial Engineering Consulting Corporation, Wuhan Hubei 430071 ,China China University of Geosciences(Wuhan) ,Faculty Engineering,Wuhan Hubei 430074 ,China Hubei Sanning Mining Co. , Ltd. , Yichang Hubei 443100,China)
出处 《化工矿物与加工》 北大核心 2017年第9期33-36,共4页 Industrial Minerals & Processing
关键词 磷矿 胶结充填 强度设计 工程类比 理论计算 phosphate rock cemented fill strength design engi- neering analogy theoretical calculation
  • 相关文献

参考文献10

二级参考文献44

共引文献355

同被引文献28

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部