摘要
在极不规则锯齿形工作面缩架、综机设备搬家(跳切眼)工作中,柴里煤矿为缩短停产时间,采取边生产、边安装,两巷同步施工的方法,缩短了工作面搬家时间,降低了生产费用。
In the very irregular serrated face shrinkage rack, the machine moving (jump cut eyes) work, in order to shorten the cut-off time, ChaiLi coal mine has taked edge production, side installation, two lane synchronous construction method, shorten the working time of the face moving and reduces the production cost.
作者
王超
贾广军
季德军
Wang Chao-jia Guang-jun Ji De-jun(Zaozhuang Mining Industry (Group) Co., Ltd. Firewood coal mine, Shandong Zaozhuang 277519)
出处
《山东煤炭科技》
2017年第9期39-39,42,共2页
Shandong Coal Science and Technology
关键词
综采
撤面
安装
fully mechanized from surface installation