某地下超长组合池结构无缝设计研究

Research on the seamless design of an underground super-long combined pool structure
下载PDF
导出
摘要 某污水厂组合池为例,总结超长水池无缝设计的各种措施,给出了参数的选取和相应温度应力的计算。通过计算证明了设置后浇带、降低板厚、掺加外加剂等措施,对超长水池温度应力的释放有着重要作用。采取合理措施,降低混凝土温差及收缩产生的温度应力,并通过提高混凝土的极限拉伸应变,可以避免结构出现温度裂缝,从而实现超长水池的无缝设计。 Based on the example of a sewage plant, various measures of seamless design of super-long pools were concluded, parameters were selected, and corresponding heat stress was calculated. Through calculation, measures like installing post-cast strip, reducing slab thickness, adding admixture and so on were proved significant to the release of the heat stress of super-long pools. It's shown that suitable measures, lower temperature range of concrete and temperature stress caused by contract, higher ultimate tensile strain could avoid situations like thermal cracking in the structure,thus the seamless design of super-long pools could be achieved.
作者 胡胜良 李锐 Hu Shengliang Li Rui(China Machinery international engineering design&reserach Co. , Ltd. , Nanjing 210023)
出处 《工程建设》 2017年第8期52-55,共4页 Engineering Construction
关键词 超长水池 无缝设计 后浇带 温度应力 裂缝 super-long pool post-cast strip heat stress crack seamless design
  • 相关文献

参考文献2

二级参考文献8

共引文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部