摘要
结合工程实例,简述了大断面、浅埋、偏压、施工干扰大、防水要求高的隧道施工各阶段的监理工作监控重点,并提出了相应关键工序、重要部位的控制内容。
Based on an engineering example, the key supervising points in each phase of shollow - buried ec- centric compression tunnel with characteristics like large section,large consruction disturbance and high waterproof requirements were introduced, according key procedures and control centents of key parts were put forward.
作者
张明太
Zhang Mingtai(Hunan Hetian Engineering Project Management Co. ,Ltd. , Changsha 410007)
出处
《工程建设》
2017年第8期80-83,共4页
Engineering Construction
关键词
城市隧道
大断面
施工监理
控制要点
urban tunnel
large section
construction supervision
key control point