对文物电厂——云南开远南桥电厂压力钢管更新改造的实践

On the Renovation of Historical Relic Hydropower Plants-A Practical Case of the Penstock Renovation in Yunnan Kaiyuan Nanqiao Hydropower Plant
下载PDF
导出
摘要 云南开远南桥电厂是继昆明石龙坝水电站、吉林丰满水电站之后的中国第3座水电站。电站于1937-02-18日开工,1942年落成。引水压力钢管由于年久锈蚀漏水,需要更新改造。但该电厂属文物保护单位,故压力钢管更新改造具有特殊性,要求外观应达到"更新如旧"的效果,经过精心研究、探讨与实践,达到了预期目的。 Yunnan Kaiyuan Nanqiao Hydropower Plant is the third hydropower station built in China, which is comple- ted in 1942. Due to its old age, serious corrosion and water leakage are found in the water diversion penstock. As a his- torical conservation relic, renovation of the power plant must follow the concept that "renovated as the original in appear- ance". Thus, special renovation measures are proposed and implemented. Practice shows that the renovation is satisfac- tory.
作者 戴钧 DAI Jun(Ynnnan Kaiyuan Yihang Electric Power Co. Ltd. , Kaiyuan 661600, China)
出处 《水电与新能源》 2017年第9期32-38,共7页 Hydropower and New Energy
关键词 开远南桥电厂 文物保护单位 压力钢管 更新改造 Kaiyuan Nanqiao Hydropower Plant historical conservation relic penstock renovation
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部