摘要
南水北调中线一期工程总干渠沙河南至黄河南段(委托建管项目)潮河段,设计桩号SH(3)133+380.8~SH(3)179+227.8,沿线地质情况复杂多样,针对施工过程中遇到的弱膨胀岩土渠基,采取了相应的处理措施,处理效果显著。
The designed pile number is SH(3 ) 133 + 380 ~ SH(3 ) 179 + 227 in the Chaohe River section from south of Shahe River to south of Yellow River ( entrusted construction and management project) of South-to-North Water Diversion Mid-line Stage I Project mairl canal. The geological conditions are complex and diversified along the project. Corresponding treatment measures are taken with remarkable effect aiming at weak expansive rock soil canal foundation in the construction process
出处
《水利建设与管理》
2017年第9期13-15,共3页
Water Conservancy Construction and Management
关键词
南水北调
膨胀岩土
处理措施
South-to-North Water Diversion
expansive rock soil
treatment measures