剥采关系与进度计划的探讨 被引量:1

Discussion on stripping relationship and progress plan
下载PDF
导出
摘要 对抚顺东露天矿生产过程中实际经验进行分析,对剥采关系宏观控制和微观控制的方法及必要性进行了论证,探讨了影响剥离物与采出物关系的几个因素。同时分析了采剥进度计划对每年的采出量、剥采比、开拓方式、各开拓水平间关系的影响。 Through the practical experience in the process of production in Fushun East Open-pit Mine, the article demonstrates the method and necessity of the stripping relations macroscopic control and microscopic control, and discusses several factors of affecting the stripping and recovery content. At the same time, the author analyzes the effect of stripping schedule on recovery, stripping ratio, pioneering way, the relationship between the development level each year.
作者 孙鹏 姜汉磊 闫岽 李东升 吴明轩 SUN Peng JIANG Hanlei YAN Dong LI Dongsheng WU Mingxuan(East Open-pit Mine, Fushun Mining Group Co., Ltd., Fushun 113003, China)
出处 《露天采矿技术》 CAS 2017年第9期49-51,共3页 Opencast Mining Technology
关键词 露天矿 剥采比 采剥进度计划 open-pit mine stripping ratio stripping schedule
  • 相关文献

参考文献4

二级参考文献3

  • 1[1]中国矿业大学.露天采矿手册(第五册)[M].煤炭工业出版社,1986.
  • 2东露天矿初步设计[R].
  • 3露天采矿手册[M].

共引文献31

同被引文献6

引证文献1

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部