期刊文献+

多基坑同时施工对相邻地铁线路的叠加效应影响及控制措施 被引量:5

Influence of Superposed Effect on Subway by Simultaneous Construction of Multiple Foundations and the Control Measures
下载PDF
导出
摘要 随着城市建设步伐的加快,不可避免地会出现邻近地铁线路的多个基坑同时施工的情况。为确保既有地铁线路结构及运营安全,有必要研究邻近地铁线路的多个基坑同时开挖对地铁线路结构产生的叠加效应。上海长泰国际广场项目和浦东软件园三期A1地块综合商业配套项目分别位于上海轨道交通2号线金科路站两侧,两个项目的基坑同时施工,对比分析了施工阶段对桩基、围护、加固、基坑开挖、地下室回筑等进行监测的数据,在此基础上分析了邻近基坑开挖对2号线金科路站车站及附近隧道结构变形的叠加效应,并制定了有效的监护方案及防护措施。 With the rapid pace of urban development,the simultaneous construction of multiple foundations adjacent to metro lines is inevitable. In order to ensure the structure and operation safety of the existing subway line, it is necessary to study the superposed effect of adjacent foundation pits and develop a targeted monitoring proposal. By data comparative analysis of Changtai International Plaza and Shanghai Pudong Software Park Phase 19, such as piling, maintenance, reinforcement, excavation and backfilling in the pit foundation process, a research is conducted on the superposed effect on Jinke Station of Shanghai Metro Line 2, followed by a targeted monitoring and maintenance scheme.
作者 蒋志珍
出处 《城市轨道交通研究》 北大核心 2017年第10期102-105,共4页 Urban Mass Transit
关键词 多基坑施工 叠加效应 结构变形控制 construction of multiple foundations superposed effect structure deformation control
  • 相关文献

参考文献3

二级参考文献15

共引文献37

同被引文献49

引证文献5

二级引证文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部