摘要
随着我国机电设备设计、制造及施工工艺等综合实力的提高,我国机电产品已应用于国际工程。本文结合CCS水电站500 kV电缆现场交接试验及所选试验设备参数估算做一个陈述,所取得的工程经验,对同类电站的工程建设具有借鉴意义,供同行参考。
Along with the enhancement of China's comprehensive strength in design,manufacturing and construction technique of M&E equipment,Chinese M&E products have been applied to international projects.This paper describes the field handover test of 500 kV cable for the CCS Hydropower Station and the parameter estimation of test equipment selected.The engineering experience acquired from the Project can be used for reference during the construction of hydropower projects of the same type.
出处
《水电站机电技术》
2017年第10期19-22,共4页
Mechanical & Electrical Technique of Hydropower Station