摘要
预制装配式地铁车站具有施工速度快、占地少节省劳动力等优点的同时也具有预制构件自重大,形状特殊等不利因素。为进一步提高拼装效率、质量,经济和安全性,通过对国内预制装配式地铁车站—长春地铁2号线西兴站现场施工研究,以及对地铁车站的拼装工艺、拼装设备和拼装步序进行了理论分析,制订合理的拼装工艺以确保其安全高效地完成施工。
Prefabricated subway station has the construction speed is quick, covers an area of less Labour saving at the same time also has a prefabricated from adverse factors such as material, shape, special.In order to further improve the efficiency of assembly,quality,economy and security, through to the domestic prefabricated subway Station-Changchun Subway Line 2 xixing station site construction research,as well as the assembly process of the subway station, assembly equipment and assembly step sequence are analyzed theoretically, make a reasonable assembly process to ensure its safe and effective to complete the construction.
出处
《建筑技术开发》
2017年第09X期74-75,共2页
Building Technology Development
关键词
预制装配式
地铁车站
拼装施工
prefabricated assembly
subway station
assembly construction