蒙库尾矿坝下游坝坡渗水现象分析及处理措施

Processing measures and phenomenon analysis of seepage in the downstream slope of Mengku tailings dam
下载PDF
导出
摘要 针对蒙库尾矿坝940 m标高平台出现的严重渗水现象,分别采用水力学方法和数值模拟方法计算尾矿坝浸润线位置,两种方法计算的结果基本一致。针对此严重渗水事故,提出采用轻型井点法降低浸润线,效果较为理想,对尾矿坝类似事故的处理有一定的借鉴意义。 In allusion to the serious seepage phenomenon in the platform with 940 m elevation in Mengku tailings dam, the location of saturation line in the tailings dam was calculated using the hydraulic method and numerical simulation respectively, and the results of the two methods are basically the same. In this paper, light well point method was put forward to reduce the infiltration line, and the effect is more ideal, which had certain referential sig- nificance for treatments of similar accidents of the railings dam.
作者 周福强 于广明 宋琨 谢焦焦 Zhou Fuqiang Yu Guangming Song Kun Xie Jiaojiao(School of Civil Engineering, Qingdao University of Technological, Qingdao 266000, Shandon)
出处 《工程建设》 2017年第9期68-71,共4页 Engineering Construction
关键词 渗水现象 浸润线 水力学法 数值模拟 轻型井点法 seepage phenomenon saturation line the hydraulic method numerical simulation light well point method
  • 相关文献

参考文献3

二级参考文献8

共引文献69

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部