摘要
长沙县水渡河河坝改造工程中不断创新,采取把升卧式平面闸门作为启闭机平台施工工作平台的方法进行施工,大大降低了工作桥的排架高度,从而加快了施工进度,降低了工程成本,保证了工程质量。在施工结束后,公司总结了在此次施工中的经验,形成了"利用升卧式平面闸门进行启闭机平台施工工法"。
Changslia County Shuidu River Dam modification worlc is constantly innovated. Elevation horizontal plane gate isadopted as a hoist platform construction method, and the framed bent height of service bridge is greatlaccelerating construction progress, reducing the engineering cost, and guaranteeing the engineering quality. After theconstruction is completed, the company summarizes the experience in the construction. The method of ' utilizing elevationhorizontal plane gate for hoist platform construction’ is formed.
出处
《中国水能及电气化》
2017年第10期35-45,共11页
China Water Power & Electrification
关键词
水渡河河坝改造
启闭机平台施工
平卧式平面闸门
Shuidu River dam reconstruction
construction of hoist platforn
flat horizontal plane gate