摘要
以陕北地区某矿主井冻结工程为参照原型,将相似理论和模型试验的研究方法应用于饱和砂层冻结壁解冻过程,进而探求解冻过程中的井筒致灾因素,为饱和砂层冻结施工和解冻阶段施工工艺改进提供试验依据。
To explore the cause of inclined shaft failure factor in the thawing process and provide experimental basis for freezing construction in saturated sand and improvement of construction technology in thawing stage, the similarity theory and model test are applied to the frozen wall thawing process, which refers to a main shaft freezing engineering of a coal mine in northern Shaanxi.
出处
《煤炭技术》
北大核心
2017年第11期67-69,共3页
Coal Technology
基金
陕西省工业科技攻关项目(2016GY-148)
关键词
饱和砂层
冻结壁解冻
模型试验
saturated sand
thawing of frozen wall
model test