期刊文献+

浅埋深水体下巷道掘进安全性论证与实践

Demonstration and practice of roadway safety under water
下载PDF
导出
摘要 通过对荥经县更兴煤业有限责任公司开采技术条件条件的分析,得出了主平硐的开挖对余家坝水电站引水渠及余家坝小溪产生影响的条件;通过松动圈法计算出了主平硐开挖后所形成的松动圈半径,通过自然平衡拱法计算出了主平硐开挖后所形成的平衡拱高度,并提出了主平硐掘进方案的可靠性分析与安全技术措施,为该矿及其它类似条件下的巷道掘进设计提供了参考。 Through the analysis of Yingjing County Hing more coal limited liability company mining technology conditions, the influence of theexcavation of the main adit of Yujiaba Hydropower Station Diversion Canal and Yujiaba stream generated by conditions; loose circle method tocalculate the radius of loose zone formed by the main adit excavation, calculated the formation of the main adit excavation after the balancearch height through natural arch method, and puts forward the main adit excavation scheme of the reliability analysis and safety technicalmeasures, providea reference for the design of the mine roadway excavation and other similar conditions.
作者 杨波 焦生淘 Yangbo;Jiao shengtao(Sichuan Coal Design and Research Institute , Chengdu 610031)
出处 《煤矿现代化》 2018年第1期133-134,137,共3页 Coal Mine Modernization
关键词 水体下 松动圈 自然平衡拱 爆破震动 Water body Loose ring Natural balance arch Blasting vibration
  • 相关文献

参考文献5

二级参考文献40

共引文献164

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部