摘要
通过水力学模型试验分析了中川水电站泄洪闸的泄流能力及其影响因素,试验从上游引渠开挖范围、左导墙型式和泄洪闸体型等方面进行了优化,有效改善了进闸流态,解决了原方案设计能力严重不足的问题。
Through the hydraulic model tests,the discharge capacity and its impact factors of the flood discharge gate,ZHongchuan Hydropower Project are analyzed. In the tests,the excavation range of the approach channel at upstream,left guide wall type and flood discharge gate outline,etc are optimized. These effectively improve the inflow pattern and solve the issue of insufficient discharge capacity in the existing design scheme.
作者
刘锦
张晓莉
严谨
LIU Jin;Z H A O Xiaoli;Y A N Jin(Northwest Engineering Corporation Limited,Xi'an 710065, China)
出处
《西北水电》
2017年第5期74-77,81,共5页
Northwest Hydropower
关键词
泄洪闸
泄流能力
流量系数
体型
优化
中川水电站
flood discharge gate
discharge capacity
flow coefficient
outline
optimization
Zhongchuan Hydropower Project