摘要
蒲城电厂厂区一期工程自建成投入使用以来,厂区内各建筑物一直处于变形状态,不断的下沉。对厂区内各建筑物的不均匀沉降进行分析,探讨其不均匀沉降原因,为湿陷性黄土地区地基处理方案提供可靠依据。
Since the first stage project of Pucheng power plant has been built and put into use, the buildings in the plant have been in a state of deformation and sinking continuously. In this paper, the uneven settlement of buildings in the plant area is analyzed, and the causes of uneven settlement are discussed, in order to provide a reliable basis for the foundation treatment of collapsible loess area.
作者
聂守智
Nie Shouzhi(XV an Engineering Investigation and Design Research Institute of China National Non-Ferrous Metals Industry, Xi'an 710054, China)
出处
《山西建筑》
2017年第31期59-61,共3页
Shanxi Architecture
关键词
不均匀沉降
地基处理
黄土湿陷性
uneven settlement, foundation treatment, collapsibility of loess