摘要
基于某酒店建设工程项目,分析了钢管柱混凝土顶升浇筑施工需要解决的问题及施工关键点,详细阐述了混凝土顶升浇筑施工的具体流程及工艺,施工中采用了截止阀门、钢管柱防振动、防止混凝土孔洞等多个预防措施,顺利完成了该项目钢管混凝土柱施工,并经过相关安全监督检验中心检查合格。
A hotel construction project based on the analysis of the concrete filled steel tube jacking construction problems need to be solved and construction key points, elaborates the concrete process and the process of hoisting concrete pouring construction, used in the construction of steel pipe column stop valve, anti vibration, prevent concrete holes and many other preventive measures, the successful completion of the construction project of the concrete-filled steel tube column, and after the relevant safety supervision and inspection center of the inspection.
作者
张秀莉
Zhang Xiuli(Shanxi st Construction Group Co., Ltd,Taiyuan 030012, China)
出处
《山西建筑》
2017年第31期78-79,共2页
Shanxi Architecture
关键词
钢管混凝土
混凝土浇筑
顶升
自密实混凝土
concrete-filled steel tube, concrete pouring, jacking, self compacting concrete