基于最小二乘法拟合的立式水电机组盘车计算新方法 被引量:1

A New Turning Gear Calculation of Vertical Hydropower Units Based on the Least Squares Method
下载PDF
导出
摘要 针对水电机组盘车计算传统方法不够准确的缺点,利用最小二乘拟合原理,将盘车过程实测的多个位置参量进行正弦函数拟合,算出对应的最大倾斜值及对应倾斜角度,为后续绝缘垫刮削或加垫奠定基础。该方法在白沙电站机组盘车过程中得到应用,实践表明该方法计算简单、结果准确,有效地提高了盘车质量。 Because the traditional method of hydropower units turning gear calculation is not accurate,this paper is using the position parameters which measured by fitting the turning process to fit the sine function based on least squares method,and calculate the maximum value and the corresponding tilt angle,which lay the foundation for subsequent insulation pad scraping.This method has been applied in the turning gears calculation in the Baisha hydropower station,and the practice shows that this method is simple,accurate,and improve the quality of turning gear effectively.
作者 黄伟平 林滨 HUANG Wei - ping;LIN Bin(Fujian Mianhuatan Hydropower Development Co. Ltd. , Longyan 364000, Fujian, Chin)
出处 《水利科技与经济》 2017年第10期51-54,共4页 Water Conservancy Science and Technology and Economy
关键词 立式水电机组 盘车 最小二乘法 摆度分析 vertical hydropower units turning gear least squares method throw analysis
  • 相关文献

参考文献3

二级参考文献13

  • 1GB50026-2007工程测量规范[S].北京:中国计划出版社,2008.
  • 2GB/T8564-2003.水轮发电机组安装技术规范[S].[S].,..
  • 3林焕森.水电机组盘车摆度特性的研究[J].水电机电安装技术.1980(1).
  • 4林焕森.水电机组任意角盘车的摆度计算问题[J].冰电机电安装技术.1980(4).
  • 5林焕森.水轮发电机组轴线位置的确定.云南电力技术,1982(3).
  • 6水电部第六、第四工程局.水轮发电机的安装[M].北京:水利水电出版社,1978.
  • 7GB/T8564-2003水轮发电机组安装技术规范[S].中国电力出版社,2003.
  • 8水利水电基本建设工程单元工程质量等级评定标准第3部分水轮发电机组安装工程[M].北京:中国电力出版社,2012.
  • 9DL5278-2012水电水利工程达标投产验收规程[S].北京:中国电力出版社,2012.
  • 10王浩,雷京祥,罗杰.三峡右岸电站东电机组轴线调整简要分析[J].水利水电技术,2009,40(1):97-101. 被引量:7

共引文献12

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部