摘要 沙特拉比格2×660 MW燃油电站地基为特殊的珊瑚礁灰岩。运用现场钻探、平板载荷试验、波速测试等勘探手段和方法,进行了重度、抗压强度等室内岩土特性试验,分析了沙特红海珊瑚礁灰岩的物理力学性质。该工程成果的应用为珊瑚礁岩土特性研究及地基基础方案的选择提供了宝贵的工程经验。同时,作为涉外项目,从勘察方案制定、技术协调、现场实施等环节的运作也积累了经验,提升了涉外项目勘察设计水平,对开拓海外市场具有积极意义。 The subsurface soils underneath a proposed 2 X660 MW power plant consist of limestone of coral reef origin.In order to characterize the engineering properties of limestone of Red Sea coral reef origin,the geotechnical investigation program included field conventional test boring,plate loading test and acoustic velocity testing and laboratory unit weight,unconfined compressive strength testing.This project provides a useful case history of construction on the coral reef limestone and significant amount of experience of geotechnical investigation,coordination among different disciplines and different stake holders as well as practical execution of technical plans are accumulated.
出处 《土工基础》 2017年第5期588-590,598,共4页 Soil Engineering and Foundation
关键词 珊瑚礁 工程特性 地基 Coral Reefs Engineering Properties Foundation Soils
  • 相关文献

参考文献1

二级参考文献4

共引文献22

同被引文献123

引证文献4

二级引证文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部