跨汉宜高铁特大桥混凝土连续箱梁顶推施工工艺分析 被引量:5

Analysis of Construction Technology of Concrete Continuous Box Girder Construction in Extra-high Railway Bridge
下载PDF
导出
摘要 随着我国经济的快速发展,基础建设的进程不断加快,交通设施的建设得到了越来越广泛的关注,而桥梁施工作为道路建设中一个最重要的环节,如何在跨越公路、铁路等障碍时高起点,高标准,高质量,高效率地施工显得尤为重要。通过跨汉宜高铁特大桥的顶推段具体施工,对桥梁施工中连续梁顶推施工工艺进行阐述,探讨其工艺流程,对类似的桥梁顶推段施工作业有较高的参考价值。 With the rapid development of Chinese economy, the process of infrastructure construction is accelerating and the construction of traffic facilities has been paid more and more attention. Bridge construction is one of the most important links in road construction. Obstacles high starting point, high standards, high quality, high efficiency construction is particularly important.This paper expatiates on the construction technology of continuous beam in the construction of the bridge by means of the construction of the pusher section of the high-span railway bridge, and discusses its technological process, which has a high reference value for the similar construction work of the bridge.
作者 王士德
出处 《建筑技术开发》 2017年第11期96-97,共2页 Building Technology Development
基金 2015年山东省第四批技术创新项目(201541901169)
关键词 连续箱梁 顶推施工 工艺流程 continuous box girder push construction process flow
  • 相关文献

参考文献2

二级参考文献2

共引文献8

同被引文献31

引证文献5

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部