摘要
介绍了工民建工程中深基坑开挖支护存在的问题,分析了深基坑具体的施工方案,然后探讨了工民建工程中深基坑开挖和支护的具体措施,从而达到了提高工民建工程的施工要求,满足了建设的效果。
This paper first introduces the problems existing in excavation and support of deep foundation pit in civil engineering, analyzes the con-crete construction plan of deep foundation pit, and then discusses the concrete measures of excavation and support of deep foundation pit in civil engineering. So as to achieve the construction of civil engineering to improve the construction requirements to meet the construction effect.
出处
《山西建筑》
2017年第34期67-68,共2页
Shanxi Architecture
关键词
工民建
深基坑
开挖与支护
施工技术
workers to build, deep foundation pit, excavation and support, construction technology